Gadzhiyev Plant moves two more shops from Makhachkala to Kaspiysk

1789
1
As to Abdulvagab Papalashov, the director general of the Gadzhiyev Plant OJSC, the administration plans to start up a new tool shop in 2024 within the framework of the project on moving the plant from Makhachkala to the territory of industrial park “Kippromkaspi” located in the investment site Uytash in Karabudakhkentsky municipal district.

Another building of the forging-press shop is planned to be put into operation till the end of 2023. “Within the project on relocation of plant from Makhachkala we have already built the foundry shop building, completed the second building and thus moved all hazardous production out of the city" – Papalashov says.

At the same time, it is planned to build apartment houses with necessary infrastructure on the territory freed from the shops in Makhachkala.